The 8-Day Bathroom Remodeling ProcessEven though each bathroom project is unique, the average bathroom remodel can be done in 8 days:
DAY 1 - DEMO: Remove towel & TP holders, toilet, mirror, vanity, medicine cabinet, shower doors (if applicable), shower walls, bath tub/shower pan, and existing floor. DAY 2 - PLUMBING: Install ½” backer board on floor, change shower controls, install new bath tub/shower pan, and replace all shut off valves. DAY 3 - ELECTRICAL & CARPENTRY: Replace fan, outlets, switches, and light fixture. Install ½” backer board on shower walls. Frame new medicine cabinet and shower niche. Repair drywall as necessary throughout. DAY 4 - TILING: Tile the shower pan (if applicable) and floor. DAY 5 - TILING: Tile all shower walls and baseboard. DAY 6 - GROUT: Grout all tiled areas. DAY 7 - PAINT: Paint ceilings and walls. Seal all tile and grout. Install vanity. DAY 8 - INSTALLATION: Install new toilet, medicine cabinet(s), mirror(s), towel & TP holder(s), and shower door (if applicable). |
We offer FREE ESTIMATESRJA Floors provides dependable service and quality craftsmanship. Contact us today to schedule a FREE consultation and estimate!
Remodeling Services: |